COMMUNE DE KUMBO
DECISION N° 00700/KCD/KUMBO COUNCIL/KCITB/KUMBO/2018 of 19TH FEBRUARY 2018 Bearing the award of the Jobbing order relating to OPEN NATIONAL INVITATION TO TENDER N° 005/ONIT/KC/KCITB/FEICOM/2017 OF 09TH JANUARY 2018 FOR THE CONTROL AND SUPERVISION OF WORKS EXECUTION FOR THE CONSTRUCTION OF THREE (03) MASONRY STONES BRIDGES AND (43) REINFORCED CONCRETE RING CULVERTS IN KUMBO MUNICIPALITY, KUMBO SUB DIVISION IN BUI DIVISION, LUNCHED UNDER NORMAL PROCEDURE
Source de financement

THE MAYOR, KUMBO COUNCIL

MINDFUL OF: The Constitution;
MINDFUL OF: The decree N° 2004/275 of 24 September 2004 on the Public Contracts Code
MINDFUL OF: The Circular N° 004/CAB/PM of 30 December 2005 in relation tothe application of the Public Contracts Code.;
MINDFUL OF:The decree N° 2011/408 of 09 December 2011 organizing the Government;
MINDFUL OF The decree N° 2011/412 of 09 December 2011 reorganizing the Presidency of the Republic;
MINDFUL OF: The decree N° 2012/074 of 08 March 2012 creating, organizing and functioning of theTenders Board of Public Contracts;
MINDFUL OF: The decree N° 2012/075 of 08 March 2012 organizing the Ministry of Public Contracts;
MINDFUL OF. The circular N° 001/CAB/PR of 19 June 2012 in relation tothe award and Control of Public Contracts;
-CONSIDERING
OPEN NATIONAL INVITATION TO TENDER N° 00500/ONIT/KC/KC1TB/FEICOM/2017 OF 09th JANUARY 2018 FOR THE CONTROL AND SUPERVISION OF WORKS EXECUTION FOR THE CONSTRUCTION OF THREE (03) MASONRY STONES BRIDGES AND (43) REINFORCED CONCRETE RING CULVERTS IN KUMBO MUNICIPALITY, KUMBO SUB DIVISION IN BUI DIVISION
Article 1: That the Jobbing Order FOR THE CONTROL AND SUPERVISION OF WORKS EXECUTION FOR THE CONSTRUCTION OF THREE (03) MASONRY STONES BRIDGES AND (43) REINFORCED CONCRETE RING CULVERTS IN KUMBO MUNICIPALITY, KUMBO SUB DIVISION IN BUI DIVISION has been awarded to the enterprise herein mentioned below,as follows:

BIDDERS

DURATION

AMOUNT FCFA TTC

UNITA CONTRACTORS CO LTD

06 MONTHS

13,718 797

 Article 2: The successful bidder is requested toreport at the Kumbo Council Service ofAward for Public Contracts Office to formalize the Jobbing Order.

KUMBO Le 19-02-2018
Le MAYOR