THE PROJECT COORDINATOR
DECIDES as follows:
Article 1: The contracts for the construction of water supply schemes in the four selected production basins following the recommendation of the Special Tenders Board have been awarded as follows:
LOT |
Subject |
Contractor |
Evaluated price exclusive taxe |
Duration |
1 |
Construction of rice warehouses: 1 in Mbonso, Mbiame Council Mbaw/Mbonso and 1 in Gayama, Zhoa Council. Gayama production basin |
Emma & Sons Enterprise |
86,795,750 |
8 months |
2 |
Construction/Rehabilitation of 04 water schemes in Widikum and Gayama production basinslocated in Awi, Diche, Ngalla-Ambombo-Eka, inWidikum Council and Munkep Esu in Zhoa Council |
Trinity Enterprise |
100,158,708 |
8 months |
3 |
Construction/Rehabilitation of04 water schemes in Mbaw/Mbonso production basin at the following locations Lekep village in Nwa council, Up and Mbonso villages in Mbiame Council and Mborong village in Ndu Council |
Yoshim Enterprise |
139,680,664 |
8 months |
Article 2: The Contract Award Expert of GP-DERUDEP II is charged with the responsibility of Informing the concerned
Article 3: This decision is issued to serve the purpose it deserves