THE PROJECT COORDINATOR
DECIDES as follows:
Article 1: The contracts for the supply and installation of a palm oil mill in Widikum following the recommendation of the Special Tenders Board have been awarded as follows:
Subject |
Contractor |
Evaluated price exclusive taxe |
Duration |
Supply and Installation of a Palm oil mill in Widikum in the North West Region |
GLOBAL SERVICES CAMEROON |
200 000 000 |
7 months |
Article 2: The Contract Award Expert of GP-DERUDEP II is charged with the responsibility of Informing the concerned
Article 3: This decision is issued to serve the purpose it deserves