Système intégré de gestion ouvert et multiplateformes des marchés publics
Publié le 12-04-2021 à 17:57
Support : support@armp.cm Plateforme : pridesoft@armp.cm
COMMUNE DE MENGUEME
AVIS D’APPEL D’OFFRES NATIONAL OUVERT EN PROCEDURE D’URGENCEN°004/AONO/C-MENGUEME/CIPM/2021 DU 23/03/2021POUR L’EXECUTION DES TRAVAUX DE CONSTRUCTION DE LA LIGNE TRIPHASEE DE BENEBALOT VERS MINLABA (4KM) ET LES TRAVAUX D’ELECTRIFICATION DU TRONÇON YENESSI-FALASSI EN DEUX (02) LOTS DANS LA COMMUNE DE MENGUEME, DEPARTEMENT DU NYONG ET SO’O, REGION DU CENTREAdditif n°01
Source de financement
1 Critères d'évaluation
Au lieu de ...

        A. Main eliminatory criteria:

  1. a.       administrative offers

         1) Absence or non-conformity of an administrative document after 48 hours;

    2) Absence of a bid bond;

          3) Falsified or non-authentic document;

   b. technical offers

          1) False declaration or falsified documents;

          2) Have not met at least 80% of the qualification criteria;

          3) Non justification of a realization in the past three (03) years, as a principal contractor in electrical works.

          4) Absence of a site visit report with photos.                                                                                                                                    

        c. financial offers

    1) Incomplete financial offers;

    2) Omission of a quantified unit price in the offers;

    3) Absence of an attestation of financial capacity of an amount equal to one third of the estimated cost

Lire plutot

A. Main eliminatory criteria:

            a.  administrative offers

1)      absence or non-conformity of an administrative document after 48 hours;

2)      False declaration;

   3) Absence of a bid bond;

        4) Falsified or non-authentic document;

   b.    technical offers

              1) False declaration or falsified documents;

              2) Have not met at least 80% of the qualification criteria;

              3) Non justification of a realization in the past three (03) years, as a principal contractor in electrical works.

              4) Absence of a site visit report with photos.                                                                                                                                    

        c. financial offers

       1) Incomplete financial offers;

       2) Omission of a quantified unit price in the offers;

MENGUEME Le 12-04-2021
Le MAIRE
ONANA MBA MARTIN DESIRE