Within the framework of the execution of the 2018 State Budget, the Regional Delegate of Public Contracts for the South West hereby launches by emergency procedure, an open national invitation to tender for the construction of four (04) boreholes in two(02) lots in the South West Region by emergency procedure.
This involves the realisation of the tasks outlined in the bills of quantifies and cost estimates and elaborated in the special technical clauses comprising notably: Preliminary works involving ; Studies and mobilization
- Drilling works
- Equipment/development/pumping
- Surface/superstructures
- Equipments/Development of utility area Analysis of water quanlity
- Disinfection
- Training of a manual pump repairer Maintenance systems
Etc
The estimated cost after oreliminarv studies stands at:
LOT |
PROJECT |
PROVISIONAL |
IMPUTATION N° |
TOTAL COST TTC |
||||
|
Construction of a borehole at BABA EKOMBE |
8 |
000 |
000 |
52303930264190 |
|
|
|
UNIQUE |
|
|
|
|
62811 |
|
|
|
|
Construction of a borehole at ILLOR |
8 |
500 |
000 |
52405310764191 |
16 |
500 |
000 |
|
|
|
|
|
42811 |
|
|
|
|
Construction of a borehole at IHC of KAFJU |
8 |
500 |
000 |
52405310764190 |
|
|
|
|
|
|
|
|
22811 |
16 |
500 |
000 |
|
Construction of a borehole at BESONGABANG |
8 |
000 |
000 |
|
|
|
|
01 |
Construction of a borehole at ILLOR |
8 500 000 |
Ekondo Titi |
|
|
Construction of a borehole at IHC of KAFJU |
8 500 000 |
Akwaya |
|
02 |
Construction of a borehole at BESONGABANG |
8 000 000 |
Mamfe |
02 months |
The maximum duration of execution provided for by the Contracting Authority is two(02) months per lot. This duration is as from the date of notifcation of the service order to start work.
LOT |
PROJECT |
PROVISIONAL |
LOCALITY |
DURATION OF |
01 |
Construction of a borehole at BABA EKOMBE |
8 000 000 |
Bamuso |
02 MONTHS |
Construction of a borehole at ILLOR |
8 500 000 |
Ekondo Titi |
||
02 |
Construction of a borehole at IHC of KAFJU |
8 500 000 |
Akwaya |
02 MONTHS |
Construction of a borehole at BESONGABANG |
8 000 000 |
Mamfe |
The tender file may be consulted during working hours at the Regional Delegation of Public Contracts for the South West (located at Court junction Buea), service for procurement contracts, door 02.
The tender file may be acquired from the Regional Delegation of Public Contracts for the South West, service of procurement contracts, door 02; upon presentation of a nonrefundable freasury receipt (payable at the Regional Treasury Buea) of the amount indicated below. Such a receipt shall identify the concerned bidder.
Each bid drafted in English or French shah be signed by the bidder or by a duly authorized representative and presented in seven (07) copies including the original and six (06) copies marked as such. These shall be submitted in one sealed pack cantaining three (3) envelopes; (A: Administrative file, B: Technical file, C: Financial file). The sealed pack shah' bear no information on the enterprise, and should reach the Regional Delegation of Public Contracts for the South West in Buea, service for procurement contracta, room 02, not !citer thant 12hoo noon and should carry the inscription:
OPEN NATIONAL INVITATION TO TENDER N°011/ ONIT MINNAP /RDSWR/SWRTB/SIC/2018 07 Mars 2018
FOR THE CONSTRUCTION OF FOUR (04) BOREHOLES IN TWO(02) LOTS IN THE SOUTH
VVEST REGION BY EMERGENCY PROCEDURE.
"To be opened only during the bid-opening session"
In case of any ambiguities or differences, only the original shall be considered authentic.
The maximum duration of execution provided for by the Contracting Authority is two(02) months per lot. This duration is as from the date of notifcation of the service order to start work.
Each bidder must include in his/her administrative documents, a bid bond that respects the models of this tender file, issued by a first-rate banking establishment approved by the Ministry in charge of finance, (see list in document No. 12 of this tender file), of an amount as follows
LOT |
PROJECT |
PROVISIONAL |
TOATL COST |
BID BOND |
||||
01 |
Construction of a borehole at BABA EKOMBE |
8 |
000 |
000 |
16 |
500 |
000 |
330 000FCFA |
Construction of a borehole at ILLOR |
8 |
500 |
000 |
|||||
02 |
Construction of a borehole at IHC of KAFJU |
8 |
500 |
000 |
16 |
500 |
000 |
330 000FCFA |
Construction of a borehole at BESONGABANG |
8 |
000 |
000 |
Bid bonds for unsuccessful bidders shall be withdrawn not later than fifteen (15) days after the award of the contract and those of successful bidder shall be retained until the required performance guarantee for good execution is provided.
Each bid drafted in English or French shah be signed by the bidder or by a duly authorized representative and presented in seven (07) copies including the original and six (06) copies marked as such. These shall be submitted in one sealed pack cantaining three (3) envelopes; (A: Administrative file, B: Technical file, C: Financial file). The sealed pack shah' bear no information on the enterprise, and should reach the Regional Delegation of Public Contracts for the South West in Buea, service for procurement contracta, room 02, not !citer thant 12hoo noon and should carry the
OPEN NATIONAL INVITATION TO TENDER N°011/ ONIT MINNAP /RDSWR/SWRTB/SIC/2018 07 Mars 2018
FOR THE CONSTRUCTION OF FOUR (04) BOREHOLES IN TWO(02) LOTS IN THE SOUTH
"To be opened only during the bid-opening session"
In case of any ambiguities or differences, only the original shall be considered authentic.
VVEST REGION BY EMERGENCY PROCEDURE.
The opening of the bids in one phase shah( be done on the 02 AVR 2018 at 1:00 PM prompt in the Conference Hall of the Regional Delegation of Publics Contracts for the South West by the competent tender board.
Only bidders may attend or be duly represented by a person of their choice, who has a full knowledge of the file and mandated in that capacity.
The evaluation of bids shall be carried out in three stages:
1st Stage : verification of the presence and conformity of each administrative document;
2nd stage : Evaluation of the technical bids;
3nd Stage ANALYSES OF THE FINANCIAL
14.1-Eiirnina3ory criteria
,Abience of o
> "3
, I". .1...
.7:
n _ 2. 2 ...
.1Le
57: 7r'S'
14.2. Main qualification criferia: The evo;!_la;or-. sh::.ce o:n on p-z,c'=.finci
The evaluation of bids shall be carried t,=chnical criteria on a global mark of 100. The c:Jter;c1- ro the
candidates courd indicatively be on the
The contract shall be awarded to the bidder whose bid is in conformity to the dispositions of the tender file and on the basis of the lowest bid and technical quality in accordance with article 33 of the public contracts code.
The bidders shall remain committed to their offers during a period of ( ninety) 90 days from the deadline set for the submission of bids.
Complementary technical information may be obtained every day during working hours from the Regional Delegation ofPublic Contracts for the South West